document.write( "Question 1024218: 10 workers can do work in 20 days , when they start the work , after how many days should 5 workers leave the work so that the work would be finished in 35 days ? \n" ); document.write( "
Algebra.Com's Answer #639692 by MathTherapy(10555)\"\" \"About 
You can put this solution on YOUR website!

\n" ); document.write( "10 workers can do work in 20 days , when they start the work , after how many days should 5 workers leave the work so that the work would be finished in 35 days ?
\n" ); document.write( "
After \"highlight_green%28matrix%281%2C4%2C+2%261%2F2%2C+or%2C+2.5%2C+days%29%29\" on the job, 5 workers can leave, and the remaining 5 workers will take 35 days to complete the \"%287%2F8%29%5E%28th%29\" remaining work. \n" );