document.write( "Question 1012976: If 25 skilled men can complete a job in 8 days; 12 skilled men and 15 unskilled men can complete it in 10 days. If 3 unskilled men can do it, how long would it take them?
\n" );
document.write( " \n" );
document.write( "
Algebra.Com's Answer #629215 by MathTherapy(10552)![]() ![]() You can put this solution on YOUR website! \n" ); document.write( "If 25 skilled men can complete a job in 8 days; 12 skilled men and 15 unskilled men can complete it in 10 days. If 3 unskilled men can do it, how long would it take them? \n" ); document.write( " Time 3 unskilled men take:\n" ); document.write( " |