document.write( "Question 1006778: A farmer employee 12 men to harvest his crops they took 9days if he had employ 16men how many days it would take them ? \n" ); document.write( "
Algebra.Com's Answer #622838 by addingup(3677)![]() ![]() You can put this solution on YOUR website! Convert this to man-days. If it takes 12 men 9 days, then:\r \n" ); document.write( "\n" ); document.write( " (12 men) × (9 days) = 108 man-days\r \n" ); document.write( "\n" ); document.write( "That is, the entire job requires 108 man-days. So if we had 16 men, then: \n" ); document.write( "108/16= 6.75 days \n" ); document.write( " |