document.write( "Question 1006778: A farmer employee 12 men to harvest his crops they took 9days if he had employ 16men how many days it would take them ? \n" ); document.write( "
Algebra.Com's Answer #622836 by josgarithmetic(39620)\"\" \"About 
You can put this solution on YOUR website!
RT=J relating rate, time, amount of job\r
\n" ); document.write( "
\n" ); document.write( "\n" ); document.write( "Each man works at the same rate r.
\n" ); document.write( "Time for the 16 men is t days.
\n" ); document.write( "\"system%2812r%2A9=1%2C16%2Art=1%29\"\r
\n" ); document.write( "
\n" ); document.write( "\n" ); document.write( "Both of those are for 1 job.
\n" ); document.write( "\"12r%2A9=16rt\"
\n" ); document.write( "\"3r%2A9=4rt\"
\n" ); document.write( "\"27=4t\"
\n" ); document.write( "\"t=27%2F4\"\r
\n" ); document.write( "
\n" ); document.write( "\n" ); document.write( "\"%286%263%2F4%29days\"
\n" ); document.write( "
\n" );