document.write( "Question 984793: In Ngomongo village a piece of work can be completed by 45 workers in 10 days .They work for 4 days after which 15 workers were laid off, how many days will it take the remaining workers to complete the work ? \n" ); document.write( "
Algebra.Com's Answer #605622 by josmiceli(19441)![]() ![]() You can put this solution on YOUR website! A piece of work can be completed by 45 workers in 10 days \n" ); document.write( "1 worker would take \n" ); document.write( "The rate of working for 1 worker is: \n" ); document.write( "[ 1 job ] / [ 450 days ] \n" ); document.write( "The fraction of the job that gets done in 4 days is: \n" ); document.write( " \n" ); document.write( "----------------------- \n" ); document.write( "That leaves \n" ); document.write( "fraction of the job that is left \n" ); document.write( "---------------------------- \n" ); document.write( "There are \n" ); document.write( "Let \n" ); document.write( "[ rate ] = [ rate ] \n" ); document.write( " \n" ); document.write( " \n" ); document.write( " \n" ); document.write( " \n" ); document.write( " \n" ); document.write( "The remaining workers will take 9 days \n" ); document.write( "to complete the work \n" ); document.write( "Hope I got it!\r \n" ); document.write( "\n" ); document.write( " \n" ); document.write( " |