document.write( "Question 984793: In Ngomongo village a piece of work can be completed by 45 workers in 10 days .They work for 4 days after which 15 workers were laid off, how many days will it take the remaining workers to complete the work ? \n" ); document.write( "
Algebra.Com's Answer #605616 by macston(5194)![]() ![]() You can put this solution on YOUR website! . \n" ); document.write( "The job requires (45 workers)(10 days)=450 worker-days \n" ); document.write( "In 4 days: (45 workers)(4 days)=180 worker-days \n" ); document.write( "Still needed{ 450 worker-days - 180 worker-days=270 worker days \n" ); document.write( "There are (45-15) 30 workers left. \n" ); document.write( "For 30 workers to complete 270 worker-days: \n" ); document.write( "(270 worker-days)/(30 workers)=9 days \n" ); document.write( ". \n" ); document.write( "ANSWER: It will take 9 days to complete the work. \n" ); document.write( " \n" ); document.write( " |