document.write( "Question 984653: 30 men can make a 120 articles in 8 days working 10hours/day.if 10 men leave the work after 4 days then how many hours per day should the rest of the men work to complete the job as per the shedule? \n" ); document.write( "
Algebra.Com's Answer #605446 by josgarithmetic(39625)\"\" \"About 
You can put this solution on YOUR website!
Focus on hours, and attempt to find the one-man rate.\r
\n" ); document.write( "
\n" ); document.write( "\n" ); document.write( "\"30r%2A%288%2A10%29=120\", the 8*10 being the number of hours.
\n" ); document.write( "\"r=120%2F%2830%2A80%29=12%2F240=6%2F120=1%2F20\", the one man rate, articles per hour.\r
\n" ); document.write( "
\n" ); document.write( "\n" ); document.write( "Next, you will have the sum of two terms.\r
\n" ); document.write( "
\n" ); document.write( "\n" ); document.write( "30 men for 4 days at 10 hours per day, and then 20 men for t unknown rate in hours per days . Still at 8 hours per day. Sum must still be 120 articles.
\n" ); document.write( "-
\n" ); document.write( "\"30%281%2F20%29%2A%284%2A10%29%2B20%281%2F20%29%2A%284%2At%29=120\"\r
\n" ); document.write( "
\n" ); document.write( "\n" ); document.write( "Find t, the hours per day that those 20 remaining men must work.
\n" ); document.write( "
\n" );