document.write( "Question 980569: Hayden is a manager at a landscaping company. He has two workers to landscape an entire park, Cody and Kaitlyn. Cody can complete the project in 8 hours. Kaitlyn can complete the project in 6 hours. Hayden wants to know how long it will take them to complete the project together. \r
\n" ); document.write( "\n" ); document.write( "Write an equation and solve for the time it takes Cody and Kaitlyn to complete the project together. Explain each step.
\n" ); document.write( "
\n" ); document.write( "

Algebra.Com's Answer #601686 by josgarithmetic(39620)\"\" \"About 
You can put this solution on YOUR website!
Rate unit should be JOBs per TIME or JOBS/HOUR.\r
\n" ); document.write( "
\n" ); document.write( "\n" ); document.write( "Cody____________\"1%2F8\"
\n" ); document.write( "Kaitlyn_________\"1%2F6\"\r
\n" ); document.write( "
\n" ); document.write( "\n" ); document.write( "Rate of for both of them working together on the same task is \"1%2F8%2B1%2F6\".