document.write( "Question 976761: a work have to be complete in 10 days but 280 worker after 3 days work they complete only 1/4 of work , how much worker are required for complete the work in 10 days \n" ); document.write( "
Algebra.Com's Answer #598296 by josgarithmetic(39614)![]() ![]() ![]() You can put this solution on YOUR website! r, rate for one worker. \n" ); document.write( " \n" ); document.write( " \n" ); document.write( " \n" ); document.write( "\n" ); document.write( "Want time to be 10 days, so requirement to finish doing 3/4 job is in need of n more workers, in \n" ); document.write( " \n" ); document.write( "\n" ); document.write( "If n is how many ADDITIONAL workers, \n" ); document.write( " \n" ); document.write( " \n" ); document.write( " \n" ); document.write( " \n" ); document.write( " \n" ); document.write( " \n" ); document.write( " \n" ); document.write( " |