\n" ); document.write( "\n" ); document.write( "if 2 men OR 3 women OR 6 children can do a job in 50 days, how many days will 1 man, 2 women and 3 children take to do the job?
\n" ); document.write( "

Algebra.Com's Answer #597395 by josgarithmetic(39620)\"\" \"About 
You can put this solution on YOUR website!
M, W, C, the rates for one man, one woman, one child.\r
\n" ); document.write( "
\n" ); document.write( "\n" ); document.write( "\"system%282M%2A50=1%2C3W%2A50=1%2C6C%2A50=1%29\"\r
\n" ); document.write( "
\n" ); document.write( "\n" ); document.write( "\"system%28M=1%2F100%2CW=1%2F150%2CC=1%2F300%29\"\r
\n" ); document.write( "
\n" ); document.write( "\n" ); document.write( "The rate of people working together is the sum of their individual rates. Take it from there.