document.write( "Question 964695: All members of a crew work at the same pace. If only 4 members of the crew are working, they complete the job in 18 days. How many hours will it take all 9 members of the crew to complete the same job?
\n" );
document.write( " \n" );
document.write( "
Algebra.Com's Answer #589519 by josmiceli(19441)![]() ![]() You can put this solution on YOUR website! The rate of working for \n" ); document.write( "[ 1 job ] / ( 18 days ] \n" ); document.write( "--------------------------- \n" ); document.write( " \n" ); document.write( "to finish the job, so the rate for \n" ); document.write( "[ 1 job ] / [ 72 days ] \n" ); document.write( "---------------------- \n" ); document.write( "The rate for \n" ); document.write( "as fast as the rate for \n" ); document.write( " \n" ); document.write( "[ 1 job ] / [ 8 hrs ] \n" ); document.write( "All 9 members of the crew take 8 hrs \n" ); document.write( "to complete the same job\r \n" ); document.write( "\n" ); document.write( " \n" ); document.write( " |