document.write( "Question 956605: 70 men can dig 15000 square meter field in 5 days. How many men required to complete 22500 square meter field in 25 days. \n" ); document.write( "
Algebra.Com's Answer #584429 by lwsshak3(11628)![]() ![]() ![]() You can put this solution on YOUR website! 70 men can dig 15000 square meter field in 5 days. How many men required to complete 22500 square meter field in 25 days. \n" ); document.write( "*** \n" ); document.write( "man-days required to dig 15000 sq m field=5*70=350 \n" ); document.write( "man-days required to dig 22500 sq m field=225/150*5/25*350=105 \n" ); document.write( "men required=105/25=4.2 \n" ); document.write( " |