document.write( "Question 950626: A contractor undertakes to dig a canal, 6 kilometer long in 35 days and employed 90 men. He finds that after 20 days only 2 kilometer of canal have been completed. How many more man must be employed to finish the work in time. \n" ); document.write( "
Algebra.Com's Answer #580481 by macston(5194)\"\" \"About 
You can put this solution on YOUR website!
2000m/(90 men/20day)=1.11 m /man/day Each man digs 1.11 meters of canal per day.
\n" ); document.write( "To finish the contractor must dig 6 km-2km=4km in 35 days-20 days=15 days.
\n" ); document.write( "To dig 4 km (4000 meters)in 15 days, he must dig 4000 m/15=266.67 meters per day. At 1.11 meters per man, he needs a total of 266.67 m/1.11 m/man=241 men. He already has 90 men so he needs (241 men-90 men)=151 men.
\n" ); document.write( "ANSWER: The contractor needs to hire 151 more men to finish the canal on time.
\n" ); document.write( "
\n" ); document.write( "
\n" );