document.write( "Question 946486: 25 workers are needed to build a house in 16 days. how many days will 28 wokers working at the same rate take to build the same house? inverse proportion question solve with unitary method
\n" ); document.write( "
\n" ); document.write( "

Algebra.Com's Answer #577418 by Theo(13342)\"\" \"About 
You can put this solution on YOUR website!
unitary method involves the inverse variation equation of y = x/k\r
\n" ); document.write( "
\n" ); document.write( "\n" ); document.write( "16 = number of days = y
\n" ); document.write( "25 = number of workers = x\r
\n" ); document.write( "
\n" ); document.write( "\n" ); document.write( "equation of y = k/x becomes 16 = k/25.\r
\n" ); document.write( "
\n" ); document.write( "\n" ); document.write( "solve for k to get k = 16 * 25 = 400\r
\n" ); document.write( "
\n" ); document.write( "\n" ); document.write( "when you have 28 workers, the equation becomes y = 400 / 28 which simplifies to 100 / 7 days which is the same as 14 and 2/7 days.\r
\n" ); document.write( "
\n" ); document.write( "\n" ); document.write( "it would take 28 workers 14 and 2/7 days working at the same rate per worker.\r
\n" ); document.write( "
\n" ); document.write( "\n" ); document.write( "
\n" ); document.write( "
\n" );