document.write( "Question 938939: Pipe A fills the pool in 8 hours, pipe B fills the pool in 12 hours. If pipe A runs for 90 minutes, then pipe B is turned on , how long will it take to fill the pool?
\n" );
document.write( " \n" );
document.write( "
Algebra.Com's Answer #573263 by macston(5194)![]() ![]() You can put this solution on YOUR website! Pipe A fills \n" ); document.write( "Pipe B fills \n" ); document.write( "Convert the 90 minute fill time to hours: \n" ); document.write( " \n" ); document.write( "Pipe A fills 12.5% of pool/hr x 1.5 hours=18.75% of pool \n" ); document.write( "Together Pipes A and B fill (12.5%+8.3%)=20.8% of the pool per hour. \n" ); document.write( "After 1.5 hours of just Pipe A, 100%-18.75%=81.25% is left to fill. \n" ); document.write( "81.25% of the pool/20.8% per hour (both Pipes)=3.9 hours to finish filling. \n" ); document.write( "1.5 hours(just Pipe A) + 3.9 hours(both Pipes)=5.4 hours total to fill pool. \n" ); document.write( " |