document.write( "Question 937625: it took 4 workers 9 days to complete a renovation work.how many workers would it take to complete the same work in 6 days? \n" ); document.write( "
Algebra.Com's Answer #571044 by josgarithmetic(39617)\"\" \"About 
You can put this solution on YOUR website!
RT=J rate time job.\r
\n" ); document.write( "
\n" ); document.write( "\n" ); document.write( "Let r = work rate of one worker.\r
\n" ); document.write( "\n" ); document.write( "Let n = how many workers for the question.\r
\n" ); document.write( "
\n" ); document.write( "\n" ); document.write( "Amount of job is 1 renovation.\r
\n" ); document.write( "\n" ); document.write( "\"highlight%284r%2A9=1=nr%2A6%29\"\r
\n" ); document.write( "
\n" ); document.write( "\n" ); document.write( "That is an equation with apparently two unknown variables, but r is a factor on both sides, so it is a common factor, and the equation becomes just of one variable, n.