document.write( "Question 934502: With this question: \"If 6 men can do a piece of work in 14 days, how many men are needed to do the work in 21 days?\" How do I know when to solve it with proportions (x=9 version 1) versus with man-days (x=4 version 2) as shown below?\r
\n" );
document.write( "\n" );
document.write( "Version 1:
\n" );
document.write( "if 6 men/14 days than, than x men/21 days [set-up as a proportion problem]
\n" );
document.write( "6 men/14 days = x men/21 days [set the ratios equal to each other and cross-multiply]
\n" );
document.write( "(6)(21)=14x
\n" );
document.write( "126=14x [solve for x]
\n" );
document.write( "x=9
\n" );
document.write( "]\r
\n" );
document.write( "\n" );
document.write( "Version 2:
\n" );
document.write( "If 6 men can do the piece of work in 14 days, then one man requires (6)(14) or 84 days to do it. In
\n" );
document.write( "other words, the job takes 84 man-days
\n" );
document.write( " 1 man takes 84 days
\n" );
document.write( " 2 men takes 42 days
\n" );
document.write( " 4 men takes 21 days
\n" );
document.write( "Let x= number of men required to do the job in 21 days
\n" );
document.write( "21 times x = number of man-days required to do the job and that equals 84
\n" );
document.write( "21x=84
\n" );
document.write( " x=4 \n" );
document.write( "
Algebra.Com's Answer #567554 by josgarithmetic(39620)![]() ![]() ![]() You can put this solution on YOUR website! Part of solving this one is to be able to recognize that it is a UNIFORM RATES problem. It takes the form of R*T=J for rate, time, job. The rate also depends on how many agents are participating to do any part of the job.\r \n" ); document.write( " \n" ); document.write( "\n" ); document.write( "Assume all men work individually at an equal rate, calling this rate r, in units of JOBS PER DAYS. The 1 job is \"a piece of work\". The men being described will in the way they are distributed, complete ONE job.\r \n" ); document.write( " \n" ); document.write( "\n" ); document.write( "\"If 6 men can do a piece of work in 14 days, how many men are needed to do the work in 21 days?\"\r \n" ); document.write( " \n" ); document.write( "\n" ); document.write( "Let r be the rate for one man. \n" ); document.write( "Let n be the unknown number of men to find. \n" ); document.write( "Let j be 1 for ONE WHOLE JOB. \n" ); document.write( "Uniform rates rule here would be of the form, R*t=j, where R depends on the number of men, workers, or agents doing any quantity of job.\r \n" ); document.write( " \n" ); document.write( "\n" ); document.write( " \n" ); document.write( "That should now make sense. \n" ); document.write( "Solve for n.\r \n" ); document.write( " \n" ); document.write( " \n" ); document.write( " \n" ); document.write( "\n" ); document.write( "--- \n" ); document.write( " \n" ); document.write( " \n" ); document.write( " \n" ); document.write( " \n" ); document.write( " \n" ); document.write( " |