document.write( "Question 926422: If 6 men can do piece of work in 20days,how many extra men should engaged to do job in 15 days? \n" ); document.write( "
Algebra.Com's Answer #562241 by josgarithmetic(39617)![]() ![]() ![]() You can put this solution on YOUR website! r, the work rate for 1 man. The same 1 job is to be done in either case.\r \n" ); document.write( " \n" ); document.write( "\n" ); document.write( "Let n be the number of additional men. \n" ); document.write( " |