document.write( "Question 921645: if 15 men can do a work in 210 days . they started working but at the end 10 days
\n" );
document.write( " 15 additional men were added then in how many days they all will complete the work
\n" );
document.write( " \n" );
document.write( "
Algebra.Com's Answer #559132 by josgarithmetic(39620)![]() ![]() ![]() You can put this solution on YOUR website! The description for doing the 1 job indicates that the one-man work rate is \n" ); document.write( " \n" ); document.write( "\n" ); document.write( "Let t be the additional days that the 30 men work together.\r \n" ); document.write( " \n" ); document.write( "\n" ); document.write( " \n" ); document.write( " \n" ); document.write( "\n" ); document.write( " \n" ); document.write( " \n" ); document.write( "\n" ); document.write( " \n" ); document.write( " \n" ); document.write( "\n" ); document.write( " \n" ); document.write( " \n" ); document.write( "\n" ); document.write( " \n" ); document.write( " \n" ); document.write( "\n" ); document.write( " \n" ); document.write( "100 additional days for the 15 EXTRA MEN (meaning 30 men total) to FINISH after the first ten days. \n" ); document.write( " |