document.write( "Question 908583: A builder needs to completes a building in 50 days.with 20 person and 25 days 40% of the work is completed.How many more men required to complete the building on time \n" ); document.write( "
Algebra.Com's Answer #551122 by KlambinRonsentaswer(36)\"\" \"About 
You can put this solution on YOUR website!
Hey.I'm glad that I can help you.But my English is not very well because I'm Chinese.I hope you don't mind it.\r
\n" ); document.write( "\n" ); document.write( "40%÷20÷25 = 1/1250 [ each person's daily workload ]\r
\n" ); document.write( "\n" ); document.write( "50-25=25 [ The remaining days ]\r
\n" ); document.write( "\n" ); document.write( "(1-40%)÷(1/1250×25)-20 =10\r
\n" ); document.write( "\n" ); document.write( "OK.\r
\n" ); document.write( "\n" ); document.write( "