document.write( "Question 908127: A can complete a piece of work in 40 days and B in 60 days. A worked alone for 4 days and then B completed work along with c in 36 days. in how many days can C work alone to complete the work ? \n" ); document.write( "
Algebra.Com's Answer #550825 by richwmiller(17219)\"\" \"About 
You can put this solution on YOUR website!
4/40+36/60+36/c=1
\n" ); document.write( ".1+.6+36/c=1
\n" ); document.write( ".7+36/c=1
\n" ); document.write( "36/c=3/10
\n" ); document.write( "3c=360
\n" ); document.write( "c=120
\n" ); document.write( "4/40+36/60+36/120=1
\n" ); document.write( ".1+.6+.3=1
\n" ); document.write( "1=1
\n" ); document.write( "
\n" ); document.write( "
\n" );