document.write( "Question 908123: A can complete a piece of work in 40 days and B in 60 days. A worked alone for 4 days and then B completed work along with c in 36 days. in how many days can C work alone to complete the work ?/ \n" ); document.write( "
Algebra.Com's Answer #550816 by josgarithmetic(39618)![]() ![]() ![]() You can put this solution on YOUR website! Assigning Variables and Setting Equation To Solve:\r \n" ); document.write( " \n" ); document.write( "\n" ); document.write( "RATES \n" ); document.write( "A, \n" ); document.write( "B, \n" ); document.write( "c, \n" ); document.write( " \n" ); document.write( "\n" ); document.write( "A works alone for 4 day; \n" ); document.write( "Without A, B and c complete the work in 36 days.\r \n" ); document.write( " \n" ); document.write( "\n" ); document.write( " \n" ); document.write( "This equation uses the uniform rates rule for doing a job or task, refers to the one job counted as 1. The rule is RT=J using rate time, and job. The job to be done in the example was split into two parts... one part for 4 days and the other part for 36 days.\r \n" ); document.write( " \n" ); document.write( "\n" ); document.write( "Solve the equation for c. \n" ); document.write( " |