document.write( "Question 901268: In 5 days A can do as much work as B in 6 days. If they work together they can complete 1 work in 12 days. In how many days can they complete a work separately? \n" ); document.write( "
Algebra.Com's Answer #546605 by richwmiller(17219)\"\" \"About 
You can put this solution on YOUR website!
5a=6b,
\n" ); document.write( "1/a+1/b=1/12
\n" ); document.write( "a=26.4, b=22