document.write( "Question 897163: IT TOOK 18 MEN WORKING 8HRS A DAY TO FINIS A CERTAIN JOB IN 20 DAYS.HOW LONG WOULD IT TAKES 15 MEN WORKING 12HRS A DAY TO FINIS THE SAME JOB?
\n" ); document.write( "It took 18 men working 8 hrs a day to finish a certain job in 20 days.
\n" ); document.write( "How long would it takes 15 men working 12 hrs a day to finish the same job?
\n" ); document.write( "

Algebra.Com's Answer #544003 by richwmiller(17219)\"\" \"About 
You can put this solution on YOUR website!
All caps is rude and considered shouting on the internet.
\n" ); document.write( "It took 18 men working 8 hrs a day to finish a certain job in 20 days.
\n" ); document.write( "How long would it takes 15 men working 12 hrs a day to finish the same job?\r
\n" ); document.write( "\n" ); document.write( "18*8*20=2880 man hours
\n" ); document.write( "15*12=180
\n" ); document.write( "2880/180=16 days\r
\n" ); document.write( "\n" ); document.write( "
\n" ); document.write( "
\n" );