document.write( "Question 895791: Four A/C mechanics finish a job in 300 hrs.
\n" );
document.write( "How much time will six A/C mechanics take to do the same job.
\n" );
document.write( " \n" );
document.write( "
Algebra.Com's Answer #543076 by richwmiller(17219) You can put this solution on YOUR website! 4*300=1200 mechanic hours needed for the job \n" ); document.write( "1200/6=200 hours for 6 mechanics to do the same job\r \n" ); document.write( " \n" ); document.write( "\n" ); document.write( " \n" ); document.write( " |