document.write( "Question 74977: in a chocolate factory it took 20 workers 6 days to fil an order for chocolate valentine candy. How long would it take if there were 30 workers? \n" ); document.write( "
Algebra.Com's Answer #53862 by ankor@dixie-net.com(22740)\"\" \"About 
You can put this solution on YOUR website!
n a chocolate factory it took 20 workers 6 days to fil an order for chocolate valentine candy. How long would it take if there were 30 workers?
\n" ); document.write( ":
\n" ); document.write( "Represent the completed job in \"man-days\"
\n" ); document.write( "In this problem:
\n" ); document.write( "20 * 6 = 120 man-days
\n" ); document.write( ":
\n" ); document.write( "How many days to complete the same job with 30 men?
\n" ); document.write( "30*d = 120
\n" ); document.write( "d = 120/30
\n" ); document.write( "d = 4 days to do the same job with 30 guys.
\n" ); document.write( "
\n" ); document.write( "
\n" );