document.write( "Question 888822: 12 workers can do a piece of work in 20 days.How many workers should be added to complete the work in 16 days?
\n" );
document.write( " \n" );
document.write( "
Algebra.Com's Answer #537717 by richwmiller(17219)![]() ![]() You can put this solution on YOUR website! 12*20=240 work days \n" ); document.write( "240/16=15 workers \n" ); document.write( "so add 3 workers \n" ); document.write( " \n" ); document.write( " |