document.write( "Question 887869: If it takes 2 days for 5 workers to finish painting a wall at a rate of 6 hours per day, then how long will it take 7 workers to finish painting a wall at a rate of 7 hours per day? \n" ); document.write( "
Algebra.Com's Answer #536890 by DrBeeee(684)\"\" \"About 
You can put this solution on YOUR website!
Given;
\n" ); document.write( "It takes 5 workers 2 days to paint a wall at the rate of 6hr/day. This gives us
\n" ); document.write( "(1) 5*2*6 = 60 worker-hours to do the job
\n" ); document.write( "Now we have 7 workers working at the rate of 7 hr/day or 49 hr/day for all 7.
\n" ); document.write( "The number of days is given by
\n" ); document.write( "(2) No. of days for 7 workers = 60hr/(49hr/day) or
\n" ); document.write( "(3) No. of days for 7 workers = 1.22... days or about
\n" ); document.write( "(4) No. of days for 7 workers = 1d,5hr,23m,16s
\n" ); document.write( "
\n" );