document.write( "Question 884801: 28 men can complete a piece of work in 21 days. How many more men must be hired to complete the work in 14 days? \n" ); document.write( "
Algebra.Com's Answer #534668 by josgarithmetic(39620)![]() ![]() ![]() You can put this solution on YOUR website! Either situation is for 1 job. \n" ); document.write( "r = the rate for one man. \n" ); document.write( " \n" ); document.write( " \n" ); document.write( "\n" ); document.write( " \n" ); document.write( " \n" ); document.write( " \n" ); document.write( " \n" ); document.write( " \n" ); document.write( "Fourteen more men. \n" ); document.write( " \n" ); document.write( " |