document.write( "Question 879395: 60 persons can complete a building in 250 days . after 200 days , work stopped for 10 days . how many additional men required to finish it on same time
\n" ); document.write( "
\n" ); document.write( "

Algebra.Com's Answer #530749 by ewatrrr(24785)\"\" \"About 
You can put this solution on YOUR website!
\"N%5B1%5D+%2A+T%5B1%5D+green%28W%5B2%5D%29+=N%5B2%5D%2AT%5B2%5Dgreen%28W%5B1%5D%29\"
\n" ); document.write( "\"60%2A200%2A%28.2%29++=+N%5B2%5D%2A40%28.8%29\"
\n" ); document.write( " \"75+=+N%5B2%5D\", 15 additional men needed
\n" ); document.write( "
\n" );