document.write( "Question 873165: It takes 8 men 9 days to lay out a garden how long will it take 6 men to lay out similar garden if they work at the same rate? \n" ); document.write( "
Algebra.Com's Answer #526679 by josmiceli(19441)![]() ![]() You can put this solution on YOUR website! If 8 men take 9 days, then 1/4 \n" ); document.write( "of the number of men will take \n" ); document.write( "4 times as long, so \n" ); document.write( "---------------------------------- \n" ); document.write( "2 men take 36 days to lay out the garden \n" ); document.write( "----------------------------------------- \n" ); document.write( "3 times as many men can do this job in \n" ); document.write( "1/3 of the time, so \n" ); document.write( "---------------------- \n" ); document.write( "6 men take 12 days to lay out the garden \n" ); document.write( " \n" ); document.write( " |