document.write( "Question 860926: If 4 workers do a job in 6 days..How long will 24 workers will need do the job?? \n" ); document.write( "
Algebra.Com's Answer #518707 by josgarithmetic(39627) ![]() You can put this solution on YOUR website! Four workers for each worker having a work rate of \n" ); document.write( " \n" ); document.write( "\n" ); document.write( " \n" ); document.write( " \n" ); document.write( " \n" ); document.write( " \n" ); document.write( "\n" ); document.write( "The original unknown rate for one worker was \n" ); document.write( " \n" ); document.write( "\n" ); document.write( "Your question was, how much time for 24 workers? The rate of all 24 workers will be additive. |