document.write( "Question 857648: if it takes six men to paint a house in 21 days, how many men will be needed to paint the house in 14 days? \n" ); document.write( "
Algebra.Com's Answer #516682 by josgarithmetic(39626) ![]() You can put this solution on YOUR website! Uniform rates for task completion, R*T=J, rate, time, quantity of jobs. Your example has J=1. The job is, \"paint a house\".\r \n" ); document.write( " \n" ); document.write( "\n" ); document.write( "The first clause gives the rate for 6 men as \n" ); document.write( " \n" ); document.write( "\n" ); document.write( "Now you want a number of men, N, to spent 14 days to do the one job. \n" ); document.write( " \n" ); document.write( "and you are asked, what is N. \n" ); document.write( " |