document.write( "Question 857648: if it takes six men to paint a house in 21 days, how many men will be needed to paint the house in 14 days? \n" ); document.write( "
Algebra.Com's Answer #516682 by josgarithmetic(39626)\"\" \"About 
You can put this solution on YOUR website!
Uniform rates for task completion, R*T=J, rate, time, quantity of jobs. Your example has J=1. The job is, \"paint a house\".\r
\n" ); document.write( "
\n" ); document.write( "\n" ); document.write( "The first clause gives the rate for 6 men as \"1%2F21\" jobs per day. The rate for just 1 man alone is \"%281%2F6%29%281%2F21%29\" jobs per day.\r
\n" ); document.write( "
\n" ); document.write( "\n" ); document.write( "Now you want a number of men, N, to spent 14 days to do the one job.
\n" ); document.write( "\"highlight%28N%281%2F%286%2A21%29%29%2A14=1%29\";
\n" ); document.write( "and you are asked, what is N.
\n" ); document.write( "