document.write( "Question 846164: It takes an electrician 45 minutes to wire an office in a new office building that is being built. The electrician signed a contract to wire all offices on 6 floors of the new building. There are 50 offices on each floor. How many weeks should the electrician allow for this job if he works a standard work week(8 hours a day 5 days a week)? Express the answer in decimal form rounded to the tenths place \n" ); document.write( "
Algebra.Com's Answer #513447 by richwmiller(17219)![]() ![]() You can put this solution on YOUR website! 45/60*6*50=x hours \n" ); document.write( "x=225 \n" ); document.write( "x/8=y days \n" ); document.write( "y/5=z weeks\r \n" ); document.write( " \n" ); document.write( "\n" ); document.write( " \n" ); document.write( " |