document.write( "Question 851103: If 3 men take 4 days to dig a drain how long would it take 2 men
\n" );
document.write( " \n" );
document.write( "
Algebra.Com's Answer #512589 by josgarithmetic(39620)![]() ![]() ![]() You can put this solution on YOUR website! That would become \n" ); document.write( " \n" ); document.write( "\n" ); document.write( "3 men______________4 days \n" ); document.write( "1 man_____________4*3 days, or 12 days. \n" ); document.write( "The one-man rate of work is \n" ); document.write( " \n" ); document.write( "\n" ); document.write( "2 men? \n" ); document.write( "*The rate is \n" ); document.write( " \n" ); document.write( "\n" ); document.write( "Let t = number of days for the two men to do this job. \n" ); document.write( " \n" ); document.write( " |