document.write( "Question 845947: 300 men were engaged to complete a job in a certain number of days. But due to another assignment 15 men dropped the 2nd day , 15 more men dropped the 3rd day and so on. It takes 15 more days to finish the work now. Find number of days in which work is completed \n" ); document.write( "
Algebra.Com's Answer #511423 by richwmiller(17219)![]() ![]() You can put this solution on YOUR website! After 21 days there are no more workers. \n" ); document.write( " |