document.write( "Question 831014: Four men working together can dig a trench in 42 days. They begin the job, but one worker works only 1/2 days. How long will it take to complete the job? \n" ); document.write( "
Algebra.Com's Answer #501063 by josmiceli(19441)![]() ![]() You can put this solution on YOUR website! The rate for 4 men is 1 trench in 42 days \n" ); document.write( "Let \n" ); document.write( "by 4 men in 1/2 day \n" ); document.write( " \n" ); document.write( " \n" ); document.write( " \n" ); document.write( "---------------- \n" ); document.write( "That means there is \n" ); document.write( "of a trench left to dig after 1/2 day \n" ); document.write( "---------------- \n" ); document.write( "3 men have to finish the job \n" ); document.write( "If 4 men take 42 days to dig a trench, \n" ); document.write( "1 man takes 4 times as long, or \n" ); document.write( "3 men take 1/3 of that time, or 56 days \n" ); document.write( "Let \n" ); document.write( "men to dig \n" ); document.write( " \n" ); document.write( " \n" ); document.write( " \n" ); document.write( " \n" ); document.write( " \n" ); document.write( "It will take \n" ); document.write( "to finish the job \n" ); document.write( "---------------------- \n" ); document.write( "Hope I got it\r \n" ); document.write( "\n" ); document.write( " \n" ); document.write( " |