document.write( "Question 830703: If 8 men can work in 12 days to assemble 16 machines, how long will it take 15 men to assemble 60 machines? \n" ); document.write( "
Algebra.Com's Answer #501026 by richwmiller(17219)![]() ![]() You can put this solution on YOUR website! 3*12=96 man days for 16 machines \n" ); document.write( "96/16=6 man days per machine \n" ); document.write( "60 *6=360 man days for 60 machines \n" ); document.write( "360/15=24 days for 15 men to assemble 60 machines\r \n" ); document.write( "\n" ); document.write( " \n" ); document.write( " |