document.write( "Question 824303: If it takes 6 men 12 days to build a wall, how long will it take 12 men? \n" ); document.write( "
Algebra.Com's Answer #496262 by fcabanski(1391)\"\" \"About 
You can put this solution on YOUR website!
The wall took a total of 6*12 = 72 man days to build.


\n" ); document.write( "1 (the job) = x * 72 where x is the rate each man works.


\n" ); document.write( "1/72 = x = the amount of the wall each man builds per day.


\n" ); document.write( "1/72 * 12 = 12/72 of the wall built (by 12 men) each day. We need a total of 72/72 (1) wall.


\n" ); document.write( "72/12 = 6 days for the 12 men to build the wall.


\n" ); document.write( "You can also look at it simple. 12 men complete the wall twice as fast as 6 men. They complete the job in half the time. So 12 men complete the wall in 12/2 = 6 days. \n" ); document.write( "