document.write( "Question 815306: If 20 people did one work for 30 days to complete, then if the same work done by 25 people then how many days taken for that work? \n" ); document.write( "
Algebra.Com's Answer #490869 by richwmiller(17219)\"\" \"About 
You can put this solution on YOUR website!
20*30=600 man days
\n" ); document.write( "600/25=24 days
\n" ); document.write( "