document.write( "Question 815308: 28 workers can finish a piece of work in 45 days.
\n" ); document.write( "a)How many workers are needed if the work is to be done in 36 days?
\n" ); document.write( "b)If after 33 days, 7 of the 28 workers leave, calculate the number of days that the rest of the workers require to finish the work. \r
\n" ); document.write( "\n" ); document.write( "the answer of a) is 35 but i could not solve b)
\n" ); document.write( "
\n" ); document.write( "

Algebra.Com's Answer #490849 by richwmiller(17219)\"\" \"About 
You can put this solution on YOUR website!
28*45=1260 man days
\n" ); document.write( "a)1260/36=35 workers to finish in 36 days
\n" ); document.write( "b) 33*28=924
\n" ); document.write( "1260-924=336 work days to go
\n" ); document.write( "28-7=21
\n" ); document.write( "336/21=16 more days to finish the job
\n" ); document.write( "
\n" ); document.write( "
\n" );