document.write( "Question 811313: 5 men can complete a job in 4 days.In how many days can 10 men working at 1/4 of the previous rate complete the job. \n" ); document.write( "
Algebra.Com's Answer #488694 by josmiceli(19441)\"\" \"About 
You can put this solution on YOUR website!
5 men can complete a job in 4 days
\n" ); document.write( "-------------
\n" ); document.write( "Twice as many men can do the same
\n" ); document.write( "job in half the time, so
\n" ); document.write( "-------------
\n" ); document.write( "10 men can do the job in 2 days
\n" ); document.write( "working at the same rate
\n" ); document.write( "-------------
\n" ); document.write( "Working at 1/4 of that rate, the
\n" ); document.write( "10 men take 4 times as long, so
\n" ); document.write( "-------------
\n" ); document.write( "10 men do the job in 8 days