document.write( "Question 809610: If 18 workers sew 540 dresses in 6 weeks,how long would it take 12 workers to do? \n" ); document.write( "
Algebra.Com's Answer #487661 by richwmiller(17219)\"\" \"About 
You can put this solution on YOUR website!
18*6=108 worker weeks
\n" ); document.write( "540/108=5 dresses per worker week.
\n" ); document.write( "108/12=9 weeks\r