document.write( "Question 806193: 10 men working 3 hrs a day can complete a wall in 8 days. How many men will be required to complete 3 wall of the same size in working 8 hrs a day? \n" ); document.write( "
Algebra.Com's Answer #485720 by richwmiller(17219)![]() ![]() You can put this solution on YOUR website! 10*3*8=240 work hours to finish one wall \n" ); document.write( "3 walls would be 720\r \n" ); document.write( "\n" ); document.write( "15*8=120 per wall so we need 2 men per wall so we need 3*2= 6 men \n" ); document.write( "also \n" ); document.write( "720/120=6 \r \n" ); document.write( "\n" ); document.write( " \n" ); document.write( " |