document.write( "Question 794322: a work is done by 12 workwrs in 45 days. if after 15 days 3 workers shift another place. then how much days to complete the work. give answer with detail \n" ); document.write( "
Algebra.Com's Answer #480613 by stanbon(75887)![]() ![]() ![]() You can put this solution on YOUR website! a work is done by 12 workers in 45 days. \n" ); document.write( "---- \n" ); document.write( "# of workers and # of days are inversely related:: \n" ); document.write( "d = k/w \n" ); document.write( "45 = k/12 \n" ); document.write( "k = 12*45 = 540 \n" ); document.write( "---- \n" ); document.write( "Equation for this problem::: \n" ); document.write( "d = 540/w \n" ); document.write( "------------------ \n" ); document.write( "\"a work is done by 12 workers in 45 days\". \n" ); document.write( "Note:: Each worker does 45/12 = 15/4 of the job each day. \n" ); document.write( "---------------------\r \n" ); document.write( "\n" ); document.write( "if after 15 days 3 workers shift another place. \n" ); document.write( "Note: after 15 days (1/3) of the job is completed; (2/3) remain to be done. \n" ); document.write( "------------------------ \n" ); document.write( "then how much days to complete the work. give answer with detail \n" ); document.write( "3 workers shift another place so there are 9 workers to do (2/3) of the job. \n" ); document.write( "---- \n" ); document.write( "2/3 of the job requires (2/3)540 = 360 man/days \n" ); document.write( "---- \n" ); document.write( "Ans: 360/9 = 40 days \n" ); document.write( "-------------------------- \n" ); document.write( "Cheers, \n" ); document.write( "Stan H. \n" ); document.write( " \n" ); document.write( " |