document.write( "Question 769627: Please help me and provide explanation to further understand.\r
\n" ); document.write( "\n" ); document.write( "A construction project must be completed in 15 days. Twenty-five workers did one-half of the job in 10 days. How many workers are needed to complete the job on schedule?
\n" ); document.write( "

Algebra.Com's Answer #469010 by stanbon(75887)\"\" \"About 
You can put this solution on YOUR website!
A construction project must be completed in 15 days. Twenty-five workers did one-half of the job in 10 days. How many workers are needed to complete the job on schedule?
\n" ); document.write( "---------------
\n" ); document.write( "# of workers and # of days are inversely related.
\n" ); document.write( "----
\n" ); document.write( "Note:: \"The job\" is really (1/2) of the job.
\n" ); document.write( "----
\n" ); document.write( "n = k/d
\n" ); document.write( "--------
\n" ); document.write( "25 = k/10
\n" ); document.write( "---
\n" ); document.write( "k = 250
\n" ); document.write( "-----
\n" ); document.write( "Equation:
\n" ); document.write( "n = 250/d
\n" ); document.write( "n = 250/5
\n" ); document.write( "n = 50 (# of workers to complete 1/2 the job in 5 days)
\n" ); document.write( "================
\n" ); document.write( "Cheers,
\n" ); document.write( "Stan H.
\n" ); document.write( "================