document.write( "Question 769627: Please help me and provide explanation to further understand.\r
\n" );
document.write( "\n" );
document.write( "A construction project must be completed in 15 days. Twenty-five workers did one-half of the job in 10 days. How many workers are needed to complete the job on schedule? \n" );
document.write( "
Algebra.Com's Answer #469010 by stanbon(75887)![]() ![]() ![]() You can put this solution on YOUR website! A construction project must be completed in 15 days. Twenty-five workers did one-half of the job in 10 days. How many workers are needed to complete the job on schedule? \n" ); document.write( "--------------- \n" ); document.write( "# of workers and # of days are inversely related. \n" ); document.write( "---- \n" ); document.write( "Note:: \"The job\" is really (1/2) of the job. \n" ); document.write( "---- \n" ); document.write( "n = k/d \n" ); document.write( "-------- \n" ); document.write( "25 = k/10 \n" ); document.write( "--- \n" ); document.write( "k = 250 \n" ); document.write( "----- \n" ); document.write( "Equation: \n" ); document.write( "n = 250/d \n" ); document.write( "n = 250/5 \n" ); document.write( "n = 50 (# of workers to complete 1/2 the job in 5 days) \n" ); document.write( "================ \n" ); document.write( "Cheers, \n" ); document.write( "Stan H. \n" ); document.write( "================ \n" ); document.write( " |