document.write( "Question 762535: It takes 4 men 14 days to do a certain job. How long should it take 7 men working at the same rate to do the same job?
\n" ); document.write( "
\n" ); document.write( "

Algebra.Com's Answer #464040 by rothauserc(4718)\"\" \"About 
You can put this solution on YOUR website!
we are given that a certain job is done in 14 days by 4 men, then 1 man takes 4*14 or 56 days.....so\r
\n" ); document.write( "\n" ); document.write( "1 man takes 56 days
\n" ); document.write( "2 men take 28 days
\n" ); document.write( "7 men take 56/7 or 8 days
\n" ); document.write( "
\n" ); document.write( "
\n" );