document.write( "Question 762348: A can complite a task in 4 days,B can do the same in 5 days and C in 6 days.If they start working together and A becomes sick at second day and stopped working then how many days B and C will required to complite the task?? \n" ); document.write( "
Algebra.Com's Answer #463873 by josgarithmetic(39620)![]() ![]() ![]() You can put this solution on YOUR website! Your description is a little unclear, \"at second day\" when A quits. Assuming A quits AT THE END OF SECOND DAY, the situation goes like this:\r \n" ); document.write( " \n" ); document.write( "\n" ); document.write( "Rates as tasks per day \n" ); document.write( "A: 1/4 \n" ); document.write( "B: 1/5 \n" ); document.write( "C: 1/6\r \n" ); document.write( " \n" ); document.write( "\n" ); document.write( "Amount of task completed by end of two days: \n" ); document.write( "Amount of task for B and C to do: \n" ); document.write( " \n" ); document.write( "\n" ); document.write( "The task rate for B and C together is (1/5+1/6) tasks per day. \n" ); document.write( "Using Rate*Time=Tasks, we can find the unknown number of days for B and C to finish the remaining amount of task.\r \n" ); document.write( " \n" ); document.write( "\n" ); document.write( " \n" ); document.write( "That uses d = the number of days for B and C to do the remaining task portion. \n" ); document.write( "(Leaving the rest of symbolic steps to solve for d, to you). \n" ); document.write( " |