document.write( "Question 761036: Five men take four days to unload 5000 tons of lumber. How long will it take 8 such men to unload 10,000 tons of lumber? \n" ); document.write( "
Algebra.Com's Answer #462992 by lwsshak3(11628)![]() ![]() ![]() You can put this solution on YOUR website! Five men take four days to unload 5000 tons of lumber. How long will it take 8 such men to unload 10,000 tons of lumber? \n" ); document.write( "*** \n" ); document.write( "5 men working 4 days=20 man-days to unload 5000 tons of lumber \n" ); document.write( "to unload 10,000 tons of lumber will require 2*20=40 man-days\r \n" ); document.write( "\n" ); document.write( "How long will it take 8 such men to unload 10,000 tons of lumber? 40/8= 5 days \n" ); document.write( " |