document.write( "Question 756683: 10 masons can build a wall working 7 hrs a day in 12 days. in how many days can a work be completed by 14 persons, working 8 hrs a day\r
\n" );
document.write( "\n" );
document.write( "can u explain this summmmmm
\n" );
document.write( "pls
\n" );
document.write( "i am a 8th grader
\n" );
document.write( "i want it now urgent!!!!!!
\n" );
document.write( "i had sent u once but dint answer
\n" );
document.write( "pls answer \n" );
document.write( "
Algebra.Com's Answer #460377 by Alan3354(69443)![]() ![]() You can put this solution on YOUR website! 10 masons can build a wall working 7 hrs a day in 12 days. in how many days can a work be completed by 14 persons, working 8 hrs a day \n" ); document.write( "-------------- \n" ); document.write( "10 masons can build a wall working 7 hrs a day in 12 days. \n" ); document.write( "7 hr * 12 days = 84 hours \n" ); document.write( "10*84 = 840 man-hrs to build the wall \n" ); document.write( "---- \n" ); document.write( "14 men * 8 hr = 112 man-hrs/day \n" ); document.write( "840/112 = 7.5 days \n" ); document.write( " |